Now a days, the power company's require a questionnaire about projected load.  I always spec two transmitters running TX rated power, not licensed power (test purposes into the dummy load.), plus double the initial design of all other loads including HVAC.  Usually that nets at least a doubling of the transformer size and resolves any issues with source impedance of the supply.

MM

On 6/20/2012 9:21 AM, Dana Puopolo wrote:
>At 850 in Boston, we bought 4160 volts from the electric company and ran out
>own step down transformers. Our generator was also 4160 and before the step
>downs.  The draw at 4160 was between 20 and 30 amps with everything on.